Permission to Operate, Milestone 8, is the last Milestone Indicator in the Portal. It will remain gray/black until PTO is claimed.
SUBMISSION AND ADVANCEMENT REQUIREMENTS
- The Dealer will utilize the "Claim PTO" link found under Milestone Indicator 8.
-
The Underwriting Team will be notified via Zendesk that PTO has been claimed and will begin the review process.
-
- PTO Approved - the loan will remain in PTO status.
- PTO Not Approved - the loan status will be reverted to "Funded"
-
- As per the Partnership Contract, after 90 days without PTO, Almika has the ability to offset the entire project.
HOW TO CLAIM PTO
- Click the Milestone Indicator for "PTO Complete/Claim PTO".
- Change the indicator to confirm "This project has PTO".
- Upload the PTO letter using the "Upload PTO Letters" button.
- Fill out the First and Last Name fields with the name of the Dealer Agent
- For "PTO Achieved Date", use the date listed in the PTO letter.
HELPFUL LINKS
- See Deliverable 6 for information on satisfying the requirements to complete this stage of the Project Lifecycle.
Comments