DEADLINE: Within 60 days of NTP.
INSTALLER DELIVERABLES:
1. Installation of the Solar System has been completed, and notification to Almika has been delivered.
2. All Permits and other applicable approvals, including but not limited to HOA approvals, have been granted and notification to Almika has been delivered.
3. Final System Details:
3.1. System Size (kW)(DC)
3.2. Expected Monthly production (kWh)
3.3. Tilt, Azimuth, and Shade
3.4. Modules (Quantity, Make, Model, Capacity)
3.5. Inverter(s) (Quantity, Make, Model, Capacity)
3.6. Battery Storage System(s) (Quantity, Make, Model, Capacity)
Almika reserves the right to set off/net fund any partial payments or payments for materials made if the system is not fully installed within the deadline listed above, or cancel the contract.
Non-approved items (i.e. other home improvement products, cash outs, vacations, etc.) cannot be financed and will be deemed a failure of this condition.
CONSUMER REQUIREMENTS
- Statutory recission periods related to Loan Agreement and Home Improvement Contract have expired.
OTHER CONDITIONS
- Installation and Testing. Solar System has been fully installed, tested, and commissioned and has been shown capable of operating in a reliable and continuous manner for its intended purpose and producing electricity in the estimated amounts.
- Title to System. Legal title to and control of the Solar System has been conveyed to Consumer with no other liens and encumbrances.
- Ready for Interconnection. There are no known issues or reasons that would cause the Solar System to not be able to be interconnected and receive Permission to Operate from the Utility.
- No Breach. Contractor is not in material breach of any obligations under the Program Agreement.
- Compliant Installation. Solar System has been designed and installed in strict compliance with the requirements of:
- The Program Agreement
- The Program Specifications
- The Project Specifications
- Applicable Law (including national, state, and local engineering, construction, safety and electrical codes and standards)
- Applicable Utility requirements (include net metering rules)
- Good Solar Industry Practices
- Contract Compliance. The Installation was performed in compliance with the applicable Home Improvement Contract, including Job Site clean-up.
- Equipment. All equipment incorporated into the Solar System is new, unused, and undamaged.
- True Representations. Contractor's representations and warranties in the Program Agreement are true.
0% of Installer Price is paid at the completion of this Milestone/Deliverable.
This corresponds to Milestone 4 in Exhibit B: Form of Program Specification found in the Dealer Contract.